During the summer of 2019, KPC completed a HVAC system change out and renovation of North Oconee High School. The Scope of work included changing out 44 roof top, 127 classroom units as well as 100,000 sf of ceiling demo and installation. KPC’s Project Team developed an aggressive 6-day per week schedule which allowed Oconee County Schools to take use of the building earlier than the dates in the contract documents. With the use of an Aircrane (Helicopter) to set the roof top units, the project team condensed 9-days of work into a single day. KPC rose to the occasion and delivered this 200,000 sf school in just 56 days.

 